- Lisa Zorn to share benefits of a two-zone versus three-zone system.
- Partners and developers to fill out Model Inventory Google Sheet, due in two weeks.
- Partners to fill out Model Evaluation Google Doc, due in two weeks.
- Code review of vehicle type model
- WSP and Elizabeth Sall are reviewing. Hoping review is done by end of next week.
- Implementation plans for school escorting
- Updating doc as they are working through the documentation
- Implementation plans for disaggregate accessibilities
- Responses have been made to comments if you want to check it out
- Added a flow chart and more description for how it works
- Document from Lisa on the benefits of two-zone versus three-zone – Lisa says it’s almost ready to share, just formatting. Lisa to share with group.
- Model Inventory Google Sheet
- Suggestions to add more detail to the sheet so that this information can be used for other purposes, such as presenting potential options to new agencies thinking of developing an ActivitySim model. Additional information requests have been added to the google sheet.
- Deadline for completion by 2 weeks
- ActivitySim Evaluation Google Doc
- Use this information, plus spreadsheet for future development of next phase of work.
- Information in older scoping workbooks that could be helpful
- Deadline for completion by 2 weeks