Task 1 Project Management (milestone)
- Discussed Phase 6 scoping here and Joe/Ben's suggestion for moving forward
- Split phase 6 into two phases - 6a July to Dec 2020; 6b Jan to June 2021
- Group / add a version 2 design task
- Toll transponders likely going away
- Multiple models test system needs more clarity
- Team agreed to phase 6 a and b rough scopes and budgets
- @RSG to scope 6a now
- @Partners continue to discuss procurement process updates offline
Task 3 Two Zones (milestone)
- Jeff getting into the task now with the example test data
- Cleaning up ability to support zone labels / non-seq zones ids in skims
Task 9 Estimation Mode (milestone)
- Continuing work on example distribution system