Skip to content

Work Periods (WP) Automation and Constraints

maxceem edited this page Jun 16, 2021 · 17 revisions

Work Period (WP) Automation and Constraints

We have to keep Work Periods in sync with data in Resource Bookings because Work Periods represent the weeks of time between Resource Bookings' start and end dates.

General rules for Work Periods:

  • Work Periods should be created, updated, deleted automatically for the Resource Bookoings, based on the Resource Bookings start/end dates
  • For each Work Period we have to calculated daysWorked automatically to reflect how many working days fit that particular week based on the Resource Bookings start/end dates (see section ResourceBooking is created for details)
  • We should be able to manually update daysWorked using endpoints to some other values other than set automatically
  • When we change Resource Bookings start/end dates, we should not re-calculate daysWorked for the Work Periods expect for the first and last Work Period if daysWorked changed for them because of the changing of the start/end dates for the Resource Booking (see section ResourceBooking startDate or endDate is changed for details)

ResourceBooking is created

Imagine we created a ResourceBooking for some work from the 1st March 2021 till 30th March 2021:

     March 2021

Su Mo Tu We Th Fr Sa  
    ˯
    1  2  3  4  5  6  
 7  8  9 10 11 12 13  
14 15 16 17 18 19 20  
21 22 23 24 25 26 27  
28 29 30 31   
      ˄

In such a case, we have to create for this ResourceBooking 5 WorkPeriods to cover all this time.

Each WorkPeriod should ALWAYS represent 1 FULL week from Sunday to Saturday and daysWorked defines how many days the member worked at that week.

Sunday and Saturday are treated as days off and should NOT be counted as daysWorked. So full week working days would be equal to 5 by default.

In the situation above, we have to create 5 WorkPeriods:

1. startDate="2020-02-28" endDate="2020-03-06" daysWorked=5 
2. startDate="2020-03-07" endDate="2020-03-13" daysWorked=5
3. startDate="2020-03-14" endDate="2020-03-20" daysWorked=5
4. startDate="2020-03-21" endDate="2020-03-27" daysWorked=5
5. startDate="2020-03-28" endDate="2020-04-03" daysWorked=2

NOTE, that WorkPeriod 5 represents the FULL week from Sunday 28 March till Satruday 3 April, but we set that in that week member worked only 2 days, because ResourceBooking was assigned only until 30 March.

WorkPeriod deleting

We should not allow deleting WorkPeriod if we fully or partially paid for it or if the payment is in progress. This means that if any associated WorkPeriodsPayment has status completed, in-progress or scheduled we should not be able to remove WorkPeriod.

ResourceBooking canceling or deleting

We should not allow canceling Resource Booking or deleting if at least one payment was already processed or in progress for at least one of the Work Period of the Resource Booking. In other words, if at least one Work Period has associated WorkPeriodPayment with status completed, in-progress or scheduled.

ResourceBooking startDate or endDate is changed

  • Once startDate or endDate is set, we don't allow removing them. Because we if remove dates, we have to remove all corresponding WorkPeriods.
  • If we extend the duration of Resource Booking by making startDate earlier or endDate later, then:
    • For existent Work Periods which are in the middle for time period DO NOT recalculate daysWorked
    • For the first and last existent Work Periods we have to recalculate daysWorked if it's changed due to startDate or endDate change
    • Just create new WorkPeriods if new weeks added to the Resource Booking, and calculated daysWorked for them
  • If we reduce the duration of Resource Booking by making startDate later or endDate earlier, then:
    • if some weeks are fully removed from the Resource Booking duration we should remove corresponding WoekPeriods
    • if currently set daysWorked is not possible - we have to update it to maximal possible as per new Resource Booking startDate/endDate.
  • ⚠️ CONSTRAINTS:
    • we should NOT allow deleting WorkPeriod if the payment for such WorkPeriod was already in-progress or completed, even if partial payment. In such case, if we try to change the dates for the Resource Booking we should return an error.

Examples for the CONSTRAINTS:

We have a Resource Booking with Start 1 March 2021 and End 30 March 2021. And we have 5 corresponding Work Periods: 4 already paid, and 1 not yet paid.

March 2021

Su Mo Tu We Th Fr Sa  
    ˯
    1  2  3  4  5  6    <- Work Period 1 - PAID
 7  8  9 10 11 12 13    <- Work Period 2 - PAID
14 15 16 17 18 19 20    <- Work Period 3 - PAID
21 22 23 24 25 26 27    <- Work Period 4 - PAID, `daysWorked` is set to `5`
28 29 30 31             <- Work Period 5 - NOT paid, `daysWorked` is set to `2`
      ˄

✅ We allow reducing ResourceBooking End to 29 March.

  • Work Period 5 daysWorked=2 would be updated to 1 to fit the new endDate of the Resource Booking

✅ We allow reducing ResourceBooking End to 24 March.

  • As a result Work Period 5 would be fully removed, which is fine because it’s not paid yet.
  • Also, Work Period 4 daysWorked=5 would be updated to 3 to fit the new endDate of the Resource Booking

❌ We don't allow reducing ResourceBooking End to 20 March.

  • This is because this would result in deleting Work Period 4 which was already paid.

Imagine we have a Resource Booking from 11 March 2021 till 23 March 2021:

March 2021

Su Mo Tu We Th Fr Sa      
    1  2  3  4  5  6
             ˯    
 7  8  9 10 11 12 13    <- Work Period 1, `daysWorked=2` (2 is maximum working days, were set automatically)
14 15 16 17 18 19 20    <- Work Period 2, `daysWorked=3` (imagine manager set working days to `3` event though it's possible to have `5`)
21 22 23 24 25 26 27    <- Work Period 3, `daysWorked=2` (imagine manager set working days to `2` event though it's possible to have `4`)
             ˄
28 29 30 31             

And we change startDate to 9 March 2021 and endDate to 30 March 2021, this would lead to the next situation:

March 2021

Su Mo Tu We Th Fr Sa      
    1  2  3  4  5  6
       ˯         
 7  8  9 10 11 12 13    <- Work Period 1, `daysWorked=4` (updated to `4`, because it was the first WorkPeriod and it have to be recalcualted)
14 15 16 17 18 19 20    <- Work Period 2, `daysWorked=3` (stays as it was before as `3` - we don't update Work Period in the middle)
21 22 23 24 25 26 27    <- Work Period 3, `daysWorked=5` (as this was the last Work Period, we recalculated days worked for it)             
28 29 30 31             <- Work Period 4, `daysWorked=2` (this Work Period has been created)
      ˄