Version 12.8.0

Compare
Choose a tag to compare
@joniles joniles released this 04 Mar 21:31
· 269 commits to master since this release
  • Add experimental support for reading Deltek Open Plan BK3 files.
  • Implemented the Relation.Builder class.
  • Marked the Relation(Task,Task,RelationType,Duration) constructor as deprecated, use the Relation.Builder class instead.
  • Marked the RelationContainer.addPredecessor(Task,Task,RelationType,Duration) method as deprecated, use the RelationContainer.addPredecessor(Relation.Builder) method instead.
  • Marked the Task.addPredecessor(Task,RelationType,Duration) method as deprecated, use the Task.addPredecessor(Relation.Builder) method instead.
  • Add a notes attribute to the Relation class and ensure that it is read from and written to P6 schedules.
  • Read the Relationship Lag Calendar setting from Phoenix 5 files. (Contributed by Rohit Sinha)
  • Don't write a material label to an MSPDI file for a resource which isn't a material.
  • Update representation of Work Variance when writing MSPDI files to more closely match output from Microsoft Project.
  • Updated to ensure that when schedules are read from XER files or P6 databases, labor and nonlabor work amounts are combined for the Actual, Remaining and Planned work attributes. This is now consistent with the existing behavior when reading PMXML files.
  • Added support for new Task attributes Actual Work Labor, Actual Work Nonlabor, Remaining Work Labor, Remaining Work Nonlabor, Planned Work Labor, Planned Work Nonlabor, when reading and writing P6 schedules.
  • Update default readAll method on reader classes to ensure that if the reader is unable to read any schedule data, an empty list is returned rather than a list containing null.
  • Ensure that Task Start and Finish dates are both the same when reading milestones from PMXML files, and that the correct date is used depending on whether we have a Start Milestone or a Finish Milestone.