You signed in with another tab or window. Reload to refresh your session.You signed out in another tab or window. Reload to refresh your session.You switched accounts on another tab or window. Reload to refresh your session.Dismiss alert
Is AGS, True
Has Nonvertical Section, True
Multilaterals Cased, True
Well Geometry Configuration, 1, -- --U-loop (could be Eavor style)
Plant Lifetime, 40, -- -Years
Water Thermal Conductivity, 0.65
Total Nonvertical Length, 6000.0
Nonvertical Wellbore Diameter, 0.23495, -- ---m
Cylindrical Reservoir Radius of Effect Factor, 5.0
Closed Loop Calculation Start Year, 0.1
Number of Multilateral Sections, 6
Well Drilling Cost Correlation, 3, -- - [-] Use built-in well drilling cost correlation #3 = vertical open-hole, large diameter
Horizontal Well Drilling Cost Correlation, 1, -- - [-] Use built-in well drilling cost correlation #3 = vertical open-hole, large diameter
Reservoir Impedance, 1E-4, -- --assume a very low reservoir impedance since the working fluid is never in contact with the reservoir
Production Flow Rate per Well, 110, -- - [kg/s]
Injection Temperature, 60, -- ---C
Gradient 1, 26.25, -- -[deg.C/km]
Reservoir Depth, 10.0, -- --km
Cylindrical Reservoir Input Depth, 10, -- ---km
Cylindrical Reservoir Output Depth, 10, -- ----km
Cylindrical Reservoir Length, 10, -- --km
Reservoir Model, 0, -- -simple cylinder reservoir model
Number of Production Wells, 1, -- -[-]
Number of Injection Wells, 1, -- -[-]
Ramey Production Wellbore Model, 0, -- - Should be 0 (disable) or 1 (enable)
Production Wellbore Temperature Drop, 0, -- - [deg.C]
Maximum Temperature, 375, -- - [deg.C]
Reservoir Volume Option, 4, -- - Should be 1 2 3 or 4. See manual for details.
Reservoir Volume, 1e9, -- - [m3] (required for reservoir volume option 3 and 4
Reservoir Heat Capacity, 1050, -- - [J/kg/K]
End-Use Option, 1, -- - [-] Electricity
Power Plant Type, 1, -- - [1] Subcritical ORC
Circulation Pump Efficiency, 0.8, -- - [-]
Plant Outlet Pressure, 68.95
Economic Model, 3, -- - Should be 1 (FCR model) 2 (Standard LCOE/LCOH model) or 3 (Bicycle model).
Fraction of Investment in Bonds, 0.65, -- - [-] Required if Bicycle model is selected. See manual for details.
Inflated Bond Interest Rate, 0.07, -- - [-] Required if Bicycle model is selected. See manual for details.
Inflated Equity Interest Rate, 0.12, -- - [-] Required if Bicycle model is selected. See manual for details.
Inflation Rate, 0.025, -- - [-] Required if Bicycle model is selected. See manual for details.
Combined Income Tax Rate, 0.392, -- - [-] Required if Bicycle model is selected. See manual for details.
Gross Revenue Tax Rate, 0, -- - [-] Required if Bicycle model is selected. See manual for details.
Reservoir Stimulation Capital Cost, 0, -- - [M$/injection well] Reservoir stimulation capital cost per injection well
Print Output to Console, 1, -- - [-] Should be 0 (don't print results to console) or 1 (print results to console)
The text was updated successfully, but these errors were encountered:
The text was updated successfully, but these errors were encountered: