How the CALC team works

See CONTRIBUTING.md as well for information on automated testing.

Tools

  • Trello
  • Github
  • Travis CI
  • Cloud Foundry

Workflow

The CALC team uses a loose Scrum framework. We have daily phone standups during our two week sprints, for which we do a sprint planning and review and retrospective.

We use a Trello board to house our product and release backlogs, as well as to keep track of progress in the current sprint. Each story is represented by a card. Stories are generated at the beginning of the project from broad hypotheses created during the planning process, and new "story candidates" can be added anytime as we build and learn.

Each sprint has its own list of cards. When a card is in progress, it should be moved to the "Working" list. After the work is complete (including documentation and automated tests as appropriate), the card should be put into the "Acceptance Testing" list until our product owner approves it.

Each card in Trello, before being worked on, should have two lists: Tasks and Acceptance Criteria. Tasks are defined during sprint planning and reflect all of the work that will need to take place to complete the feature. Where appropriate, mention team members in the task to assign it.

Acceptance Criteria should outline what the user will see and experience in order for the feature to be considered complete.

If the team decides it has the bandwidth to commit to take the story on, we move the card to the current Sprint backlog, then repeat the process until the team feels it can't take on anything else. In the event that a card is started in a sprint but not finished, it is placed back into the Release Backlog for reprioritization in a following sprint.

Before each sprint planning, our product owner sorts the cards in the Release Backlog based on their priority.

Design documents should be attached to their relevant cards for reference.

Git Workflow

We use the feature branch model. Make sure to delete feature branches after they've been merged into master so that we have a clean list of branches.

Travis CI runs automated builds that run the full test suite with each commit on a pull request. At the time of writing, there are some periodic false failures. Tests should never be ignored if they fail. Tests must be passing before merging into master. Rerun tests if necessary.

Deployment

See deploy.md for technical details.

Before each sprint planning, all changes that are to be included in the sprint should be merged into master and updated on the calc-dev Cloud Foundry app. This is so that our product owner can demo the work before accepting it.

We do blue-green deploys to our production Cloud Foundry instances after each sprint. There's no reason not to do deploys more often if desired, as long as master is kept clean.

Technical Criteria

Each set of code changes should:

  • have the full automated test suite run against them before pushing to origin
  • contain Selenium and Python unit tests where applicable
  • meet PEP8 standards