This is my story for how I came to appreciate the agile development process.

"Of all the agile methodologies, Scrum is unique because it introduced the idea of “empirical process control.” That is, Scrum uses the real-world progress of a project — not a best guess or uninformed forecast — to plan and schedule releases."

The basic idea

Thesis: Project management and software development processes can be improved. Here are areas of software implementaion that can be improved:

  • Managing Projects & Teams people skills
  • Requirements & Design eliciting & evaluating requirements
  • Process Improvement project mgmt?
  • Testing & QA
  • Development
  • Metrics
  • SOA
  • Security

No pain no gain.

Key pain areas

  • Disconnect between what the user wanted and what was developed
  • People didn't actively participate in writing or reviewing design and requirement documents
  • Large surprises would pop up and eat great swaths of development time.
  • Sometimes the large surprises didn't occur until we had the program in beta
  • Confusion about priorities. People assumed that features would be in a release, or had already been done
  • Lots of buzzwords, but not a lot of problem definition
  • Partially implemented features
  • Single developers would become wedded to their code: "for better or for worse"

Secondary pain areas

  • Poor morale due to poor reception of features and hard work
  • Much development time spent on researching the details of the feature without proper direction from users
  • Too many projects at once -- lack of focus
  • Users were despairing of ever seeing features they asked for years ago

We had failed previously

  • We had tried using an agile framework for development, but didn't use scrum.
  • We focused on reprioritizing, but didn't have a single product owner to provide a clear voice
  • We focused on getting user feedback, but then translated that into an SRS which was implemented in a waterfall method
  • We tried to sashimi our features, but we didn't timebox our development into "potentially shippable" code every 2 weeks
  • We were doing "scrum but..."

An Epiphany

Then I went to a workshop taught by Tamara Sulaiman from Applied Scrum. She had us play the "Scrum Game" where we implemented a project using the Scrum framework (in a compressed timeframe where 2 hours = one sprint) It was such a good experience I figured I'd try to bring Scrum to work.

Our process

Here's what we did:

Create the vision document for the feature

  • Get management support
  • Consensus was that we were going to focus on this feature for the project
  • Mgmt had two dates: ** 04/01/09 - demo at the Convention (6 months away) ** 05/01/09 - Enter code freeze - no new features (7 months away)
  • Reality acknowledged that smaller projects would appear in the course of the project

Gather stories.

  • Interviewed 4 offices who wanted the feature
  • Gathered stakeholders in a room to review the vision document
  • Gathered stakeholders in a room to tell stories

Talk about the stories

  • Make sure every story has a workflow
  • Story should have the form "as a (person) I want (to do something) so that (beneficial result)"
  • Keep the stories visible
  • hand out sticky pads and let everyone write
  • no more detail than fits on a sticky pad

Size the stories

  • Here's an article on estimating relative sizes
  • Similar to prioritization.
  • Assess the actual sizes of the stories. If the story will take longer than 2 weeks to implement, then it's too large: break it down
  • Get a big room
  • Put a story on the wall, then ask people whether the next story is larger or smaller
  • Position the stories by relative sizes, and it's ok to overlap
  • The stories in the middle are medium, and lower down are large and x-large
  • The stories above the medium are small and x-small
  • assign points: x-small = 1, small = 2, medium = 4, large = 8, x-large = 16

Prioritize stories

  • Get a big room
  • Put a story on the wall, then ask people whether the next story is more or less important. This is an Insertion sort
  • Talk about why it's more or less important ** Business value ( # users * potential income) ** Technical considerations (riskier sooner) ** Technical costs
  • Position the stories horizontally, and no story should overlap with another
  • When you're all done review the order, performing a bubble sort if you want to change priorities

Agree on first, second and third release milestones

  • What's the minimal functionality that can be released into the wild?
  • What's the next level after that?
  • These are critical milestones, but should tie in with business value
  • at this point you might consider cutting XL stories that are low priority

Develop a burndown chart based on sizes

  • put all the stories into a spreadsheet, on a tab called Stories
  • We didn't ever actually do the burndown chart...

Work on the #1 priority story for 2 weeks (sprint)

  • Sprint Planning - what are we working on, and how? ** The goal is to deliver value to the customer at the end of each sprint.
  • break story into functional tasks
  • Design ** Low-tech prototype ** Business rules ** UI ** Where to store this info?
  • Implement
  • Test against the story
  • Build
  • Smoke test
  • Functional and non-functional testing
  • Fix bugs
  • Add small enhancements
  • Document

Functional review with everyone that's interested

  • Review resolutions from last time
  • Present the stories
  • Discuss functionality

Process review with everyone that's involved

  • What was good about the process so far?
  • What could be improved?
  • What are we going to try to improve for the next two weeks?

Track bugs from previous sprints

Add enhancements from previous sprints as new stories

When we got to release criteria #1, release to actual beta site

Release criteria #2, give to 2nd beta site

Repeat sprints until we complete all stories, or we reach code freeze date

Comments on the process

  • If a bug is introduced during the sprint, try to fix it before the end of the sprint.
  • If the bug is discovered after the sprint, then put it in the tracking system.
  • Out of scope enhancements - put those into bug tracking system.
  • In sprint enhancements - try to incorporate according to the story
  • Out of sprint enhancements - put onto the wall (product backlog) for prioritization
  • Maintain a mirror of the wall stories in a spreadsheet. ** The spreadsheet is easier to carry around than the wall ** Helps if anyone accidentally knocks the wall features on the floor

lessons learned

  • Try to size all the stories at once, with the same units ** We were trying to estimtate the sizes in detail. ** We kept putting off sizing the stories, only doing the most immediate stories. ** Because of this, we didn't have any idea of the project burndown, since we didn't know how much work was left to do. ** 2 or 3 months into the project (of 6 months) we finally sized the remaining stories. ** Problem was, these stories had a different scale than the others, which still blows the burndown as a graphic.
  • Don't assign units. Put the stories into a spectrum from x-small to x-large. The ones in the middle are medium.
  • Write ID#s on the back of the stories. This helps keep stories associated with the spreadsheet
  • Write the whole story. If you have notes, put them on the back of the card
  • Put the stories into a value statement: "as a(n) X, I want to Y so I can Z"
  • Make sure the Product Owner really is involved.
  • 2 week sprints are essential. People rarely remembered 4 weeks ago.
  • People tend to get conversational during a daily scrum meeting, or want to solve problems. Take these items out of the scrum, scheduling them immediately after the daily scrum if necessary
  • Visibility is everything. We created an alpha station. The sales person used it, and complained about a feature. This was good.
  • Scrum is intense. It keeps you focused on the value every day. So, it's hard to find time for ** Slacking ** Web browsing ** Learning ** Wondering / Exploring
  • Instead you focus on applied learning, empirical results, and long periods of concentration.
  • This is great for productivity, but you may want to schedule some slack time.

Questions that remain

  • How to work 2 week sprints with vacations, holidays?
  • How to capture design work? Screens, business rules, programming constraints?
  • How to transistion from 2-week sprints to a released piece of software?
  • How to involve management and sales in this visibility process when they don't want to participate?
  • What happens when the project’s mostly done, but there are still small items…?
  • Still keep the sprint cycle?