Progress againsts deliverables

Phase 3 of Fab set out to work on consolidation of the Fab architecture and prepare the ecosystem for opening out to a wider developer pool.

The full phase 3 technical report contains further details.

The aims of the stage were:

  • Update the project Working Practices so as to allow Fab development to be opened up to selected collaborators at the end of the stage

  • Demonstration of a prototype extraction tool able to fetch from a MOSRS repository using an extensible architecture

  • Demonstration of an extension of the Fab infrastructure to support C code

  • Demonstration of an extensible Fab configuration file to enable flexible control of build options

  • Demonstrate support for a second Fortran compiler (stretch)

This was not directly attempted but the work on supporting C code and the extensive changes it precipitated goes a long way to achieving this.

What's going well?

  • The team continue to learn how to work together and support each other. Incidental development goals are being achieved
  • Technical progress with objectives seemingly helping to drive the overall development rather than hinder it

What could be improved?

  • Better situational awareness by the PM, the deficit being caused by juggling many other tasks.

Risks & Issues

Staff welfare

Next Phase

The proposal for phase 4 of Fab is documented on the project plan page. It is summarised as XXXXXX, running to the end of November 2020 and maintaining the same resourcing.