Long Shutdown: Overview #5979

Closed
kjwoodsISIS opened this issue Dec 14, 2020 · 11 comments
Closed

Long Shutdown: Overview #5979

kjwoodsISIS opened this issue Dec 14, 2020 · 11 comments

Comments

@kjwoodsISIS
Copy link
Contributor

kjwoodsISIS commented Dec 14, 2020

As a member of the ISIS Experiment Controls team, I want to be able to keep track of work being done on each instrument during the long shutdown (from April June 2021 to March September 2022).

At the time of creation (December 2020), this tickets notes known engineering work and expected migrations & support work. It is highly likely that circumstances will change as the long shutdown progresses. This ticket needs to be regularly updated throughout the long shutdown, to take account of changing circumstances.

@kjwoodsISIS
Copy link
Contributor Author

kjwoodsISIS commented Jan 13, 2021

Crystallography

ENGINX

  • No engineering work planned during long shutdown
  • Support: no special IBEX development anticipated.

ENGINX_SETUP

  • No engineering work planned during long shutdown
  • Support: no special IBEX development anticipated.

GEM

  • Planned engineering work:
    1. CRR testing
  • Support: no special IBEX development anticipated.

HRPD

  • Planned engineering work:
    1. HRPD repair of leak on vessel (not certain to proceed)
    2. HRPD Detector upgrade (not certain to proceed)
    3. HRPD Chopper Timing Cable installation (not certain to proceed)
  • Support: no special IBEX development anticipated.

IMAT

  • Planned engineering work:
    1. new rotation stage, requires complete setup & recommissioning
    2. Detector and Collimation Installation (not certain to proceed)
  • Support:
    1. run ENGINX stress rig after long shutdown (see IMAT: Configure & Support Instron Stress-Rig #6102).

INES

  • No engineering work planned during long shutdown
  • Support: no special IBEX development anticipated.

SXD

  • No engineering work planned during long shutdown
  • Migration: migrate SXD to IBEX (see SXD: Migrate to IBEX #6070)
  • Support: no special IBEX development anticipated (beyond what is needed for migration).

PEARL

  • No engineering work planned during long shutdown
  • Migration: migrate PEARL to IBEX (see PEARL: Migrate to IBEX #6052)
  • Support: no special IBEX development anticipated (beyond what is needed for migration).

POLARIS

  • No engineering work planned during long shutdown
  • Support: no special IBEX development anticipated.

WISH

  • Planned engineering work:
    1. Guide window replacement (not expected to impact IBEX)
  • Migration: migrate WISH to IBEX (see WISH: Migrate to IBEX #6039)
  • Support: no special IBEX development anticipated (beyond what is needed for migration).

Return to Top

@kjwoodsISIS
Copy link
Contributor Author

kjwoodsISIS commented Jan 13, 2021

Disordered Materials

NIMROD

SANDALS

Return to Top

@kjwoodsISIS
Copy link
Contributor Author

kjwoodsISIS commented Jan 13, 2021

Molecular Spectroscopy

IRIS

  • No engineering work planned during long shutdown

IRIS_SETUP

  • No engineering work planned during long shutdown

OSIRIS

  • Planned engineering work:
    1. Silicon analyser upgrade (not certain if this will proceed)
  • Support:
    1. update IBEX to support upgraded Silicon analyser (if it goes ahead).

TOSCA

VESUVIO

  • No engineering work planned during long shutdown
  • Support: no special IBEX development anticipated.

Return to Top

@kjwoodsISIS
Copy link
Contributor Author

kjwoodsISIS commented Jan 13, 2021

Excitations

LET

MAPS

  • No engineering work planned during long shutdown
  • Support: no special IBEX development anticipated.

MARI

  • No engineering work planned during long shutdown
  • Support: no special IBEX development anticipated.

MERLIN

Return to Top

@kjwoodsISIS
Copy link
Contributor Author

kjwoodsISIS commented Jan 13, 2021

SANS

LOQ

  • No engineering work planned during long shutdown
  • Support: no special IBEX development anticipated.

LARMOR

  • Planned engineering work:
    1. Replace bench motor controller with a Beckhoff
    2. Absolute encoder will be installed on the bench

SANS2D

  • Planned engineering work:
    1. Replace Baldor amplifiers
  • Migration: complete migration of SANS2D to IBEX

ZOOM

  • Planned engineering work:
    1. Replace snout. Not expected to impact IBEX.
  • Support: no special IBEX development anticipated.

Return to Top

@kjwoodsISIS
Copy link
Contributor Author

kjwoodsISIS commented Jan 13, 2021

Reflectometers

CRISP

  • No engineering work planned during long shutdown
  • Support: no special IBEX development anticipated.

INTER

  • Planned engineering work:
    1. New secondary flight path
  • Support:
    1. Update IBEX to support new secondary flight path.
    2. Continue updating reflectometry IOC in light of feedback.

OFFSPEC

  • No engineering work planned during long shutdown
  • Migration: migrate OFFSPEC to IBEX

POLREF

  • No engineering work planned during long shutdown
  • Support:
    1. Continue updating reflectometry IOC in light of feedback.

SURF

  • Planned engineering work:
    1. Engineering work is planned, but no details so far
  • Support:
    1. Update IBEX to support SURF upgrade (when we find out what is planned).

Return to Top

@kjwoodsISIS
Copy link
Contributor Author

kjwoodsISIS commented Jan 13, 2021

Muons

MUONFE

EMU

  • No engineering work planned during long shutdown
  • Support:
    1. complete implementation of support for all SE devices

MUSR

  • No engineering work planned during long shutdown
  • Support:
    1. complete implementation of support for all SE devices

HIFI

HIFI CRYOMAG

  • Planned engineering work:
    1. HIFI magnet is being re-furbished (off-site). Re-commission when it returns.

ARGUS

CHRONUS

Return to Top

@kjwoodsISIS
Copy link
Contributor Author

kjwoodsISIS commented Jan 13, 2021

RIKEN

  • Planned engineering work:
    1. Refurbishment of the RIKEN beamline (new power supplies, new PLCs)
  • Support: implement additional IOCs and OPIs to monitor equipment on refurbished RIKEN beamline (see RIKEN: Umbrella Ticket #6107).

Return to Top

@kjwoodsISIS
Copy link
Contributor Author

kjwoodsISIS commented Jan 13, 2021

Other

ALF

CHIPIR

  • Planned engineering work:
    1. compressed air (may not impact IBEX)
    2. jaws and collimator repair
    3. shutter/filter set
    4. PPS installation (may not impact IBEX)
  • Migration: migrate CHIPIR to IBEX (see CHIPIR: Final Migration #6187)
  • Support: no special IBEX development anticipated.

DETMON

  • No engineering work planned during long shutdown
  • Support: no special IBEX development anticipated.

EMMA

  • No engineering work planned during long shutdown
  • Support: no special IBEX development anticipated.

SELAB

  • No engineering work planned during long shutdown
  • Support: no special IBEX development anticipated.

SOFTMAT

  • No engineering work planned during long shutdown
  • Support: no special IBEX development anticipated.

Return to Top

@kjwoodsISIS
Copy link
Contributor Author

kjwoodsISIS commented Jan 13, 2021

Sample Environment

Chopper Group

Cryogenics

  • Planned equipment work
    1. HTS Magnet (may be complete before long shutdown) (see HTS Magnet: IOC & OPI for HTS Magnet #5577)
    2. 14T Magnet may be repaired during long shutdown. If it is repaired, its control will need to be reviewed (expected to be similar to 9T magnet). Could impact WISH
    3. Helium Recovery Monitoring
    4. New cryostat controller (no details as yet)
    5. Remote re-start of gas handling on Triton
    6. Replacement of ITC-503 by Mercury

Electronics

  • Planned equipment work
    1. Baldor amplifier replacement (see SANS2D)
    2. New jaws & sample changer on SANDALS

Pressure & Furnaces

  • Planned equipment work
    1. Yet to be advised of any plans

Soft Matter

  • Planned equipment work
    1. Yet to be advised of any plans

Return to Top

@KathrynBaker
Copy link
Member

The long shutdown is over enough that is no longer worth considering as a useful ticket.